Which conditions should trigger escalation steps written into recovery procedures?
Show the answer
Answer: C. An action overrunning its expected time, a key step completing, or items needing to be procured
SP 800-34r1 states recovery procedures should include escalation steps and points of contact for when a recovery action exceeds its expected time frame, when a key step is completed, or when items must be procured.
Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 4.3.1 Sequence of Recovery Activities