Which step does NIST include in typical recovery procedures before hardware installation begins?

  1. Declaring the end of the recovery phase to the authorising official for that one affected system
  2. Completing the after-action report that covers the activation phase of the whole plan document
  3. Deactivating the temporary recovery location that had been stood up during the course of that outage itself
  4. Obtaining authorisation to access damaged facilities and notifying business partners
Show the answer

Answer: D. Obtaining authorisation to access damaged facilities and notifying business partners

SP 800-34r1 lists recovery procedures typically including obtaining authorisation to access damaged facilities or geographic areas, notifying internal and external business partners, obtaining and installing hardware, obtaining and loading backup media, restoring critical software and data, and testing system functionality including security controls.

Source: NIST SP 800-34 Rev. 1 (NIST) — Sec. 4.3.2 Recovery Procedures